At a window the wall’s sealing layers meet the frame. The elka detail shows separate connections and places the opening in the context of the floor junction.
Trace two lines to the frame
Page 17 identifies the air seal and wind seal at the window. Start in the uninterrupted wall and follow each line across the joint. Each termination needs a defined connection to the adjoining component.
From drawing to project detail
Compare the section on page 22. Check frame position, movement, drainage and fire requirements against the actual wall assembly before adopting either detail.
Two views of the window junction
- S. 17 / p. 17
- Floor junction at the window
- S. 22 / p. 22
- Horizontal section through frame and wall